Description: To specify where work instruction update processing occurs. Setting to N4 reduces dependencies on XPS and contributes to gate operations being able to continue if XPS is offline. Setting to XPS_Server reverts to N4 sending 20005 Bento requests to XPS to update the work instruction for the gate transaction. The default is N4.
Values:
N4 - N4 handles work instruction processing (default)
XPS_Server - Rolls back to N4 sending Bento requests to XPS to update work instructions. See Rolling back N4 move processing to XPS (on page 1) for more rollback information.
Default: N4
Versions Added:3.9